What should a letter to neighbours about building work say?

Last checked 26-10-2026. A plain guide, not legal advice: check the official guidance below for your job.

Tell neighbours who you are, what you are doing, when it starts and ends, your working hours, and who to ring if there is a problem. No law makes you write the letter, but a clear one sent early heads off most complaints. A party wall notice is a separate legal step, covered below.

Why bother

Most neighbour complaints about building work come from not knowing what is happening: a skip arriving with no warning, an early start, a blocked drive. A letter costs little. It also gives people a name and a number to use before they ring the council.

Some councils ask for it. Huntingdonshire District Council, for example, asks contractors to give neighbours who may be affected by specific noisy operations at least 48 hours' notice, and to tell its environmental health team about work likely to cause disturbance. Check what your own council says.

What to include

  • Who you are and the address of the job, and who the client is if the client agrees to be named.
  • What the work is, in a sentence or two, and the expected start and finish dates. Say these are estimates.
  • Working hours, including Saturdays, and a statement that there is no noisy work on Sundays or bank holidays if that is your plan.
  • The noisy or dusty stages and roughly when they happen, such as demolition, breaking out, cutting, or digging.
  • Deliveries and access: when large vehicles or crane lorries will arrive, whether the road will be partly blocked, and how you will keep driveways clear.
  • Skips, scaffold, welfare units and storage: where they go and for how long. If they stand on the public highway you normally need a licence or permit from the highway authority. Cambridgeshire County Council, for one, requires a licence for scaffolding or hoardings and a permit for skips on the highway. Check with your own authority.
  • Parking: where the workforce will park, and a request not to block neighbours.
  • How you will control dust and noise, in a line or two.
  • A named contact with a mobile number, plus the council environmental health contact if you want to be open about it, and a promise to deal with problems quickly.

Working hours: councils vary

There is no single national rule for the hours you can do noisy work. Each council sets its own guidance or imposes conditions, and a planning permission may carry its own hours. Two examples show the spread:

  • Stratford-on-Avon District Council suggests Monday to Friday 8am to 6pm, Saturday 8am to 1pm, and no noisy work on Sundays or bank holidays.
  • Huntingdonshire District Council recommends weekdays 7am to 7pm, Saturday 7am to 1.30pm, and no noisy work on Sundays or bank holidays. It says narrower hours, such as 8am to 6pm, may be needed near sensitive neighbours.

Look up your own council's page, and read your planning conditions, before you write the hours into a letter. Put in the hours you will actually work, not the widest the council allows.

Sample letter

Use this as a starting point and change the details. The names and dates are made up.

[Date]

Dear neighbour,

Building work at 12 Brunel Terrace

We are the builders for the owners of 12 Brunel Terrace. From Monday 11-01-2027 we will be building a single-storey rear extension. We expect the main work to take about 14 weeks, finishing around mid-April 2027. These dates may change with the weather.

Working hours will be Monday to Friday 8am to 6pm and Saturday 8am to 1pm. There will be no noisy work on Sundays or bank holidays.

The noisiest stages are the demolition of the old conservatory and the breaking out of the slab. We expect these in the first two weeks. We will use dust suppression and keep the front pavement clear.

A skip will be on the owners' drive from 11-01-2027. Deliveries will come between 9am and 4pm, and we will tell you the date of any large lorry delivery in advance. Our vehicles will park on the drive and will not block your access.

If you have a concern, please ring me on [phone number] or email [email]. I will answer the same day where I can. If you have any special needs, such as a night worker sleeping in the day, please tell me so we can plan around you.

Thank you for your patience.

[Name], [Company], [Phone]

Party wall notices are separate

A neighbour letter is courtesy. A party wall notice is a legal notice under the Party Wall etc. Act 1996, which covers England and Wales. Scotland has different rules, and this guide does not cover Northern Ireland. GOV.UK says the party wall process is separate from planning permission and building regulations approval.

You must tell the neighbour if the work will build on or at the boundary, work on an existing party wall or structure, or dig below and near the foundation level of their building. Minor jobs such as plastering, replacing sockets or drilling for shelves do not need a notice.

The notice periods in the GOV.UK explanatory booklet are:

  • Party structure notice, for work to an existing party wall: at least 2 months before the work starts.
  • Line of junction notice, for a new wall at the boundary: at least 1 month.
  • Excavation notice, for digging near a neighbouring building: at least 1 month. The Act applies to digging within 3 metres, or within 6 metres where the dig meets a line drawn down at 45 degrees from the bottom of their foundations.

The adjoining owner has 14 days to respond. If they say nothing, a dispute is treated as having arisen and the Act's dispute procedure applies. A notice is valid for one year, so do not serve it too early. The duty to serve is the building owner's, not the builder's. A surveyor can serve it for the owner with written authority.

A valid notice includes the owner's name and address, the address of the building, a full description of the work, and the proposed start date. Example: if the client wants to start cutting into a party wall on 11-01-2027, a party structure notice must be served at least 2 months before, so by 11-11-2026, and allow time for delivery. Check the booklet and take advice for anything beyond the simple case.

Delivering it and following up

Keep a copy of the letter and a list of the addresses you delivered it to, and note the date in your diary.

Deliver by hand to the homes either side, the homes opposite and behind, and anyone whose access you will affect. Send it at least a week or two before the start. That timing is a suggestion, not a legal rule. Follow it up with a knock on the door where you can.

Send an update note if the programme slips by more than a week or so, or if a noisy stage moves. A short text or email to those who gave you their number is enough. Log any complaint, what you did about it, and when.