Type 1, gravel and sand calculator
How many tonnes of Type 1, gravel, sand, ballast or topsoil for an area and depth, with the bulk bags or lorry loads to order.
Put these calculators on your phone, free
They work like an app from your home screen, even with no signal on site. On an iPhone: tap Share, then Add to Home Screen. On Android: tap the menu (⋮), then Add to Home screen or Install app.
The free SiteHelm phone app for iPhone and Android is on its way, with every calculator in it. Tell me when it's out
Do more with SiteHelm PRO
Measure the area off the drawing with Take-off, then put the tonnes on a purchase order or into your quote, priced from your Book of rates. Save it to the job.
Free on your phone. Every builders' calculator will be free in the SiteHelm phone app for iPhone and Android, coming soon. Tell me when it's out.
Every builders' calculator is in SiteHelm PRO for your Windows PC, alongside take-off, RAMS, quotes, invoices and 40+ more tools. The first 100 get a free 1-year licence.
Worked example
A sub-base for a drive 6 m × 4 m, 150 mm of Type 1, with the usual extra for compaction:
8.32 tonnes of MOT Type 1 sub-base
- 24.00 m² at 150 mm deep = 3.60 m³ laid
- At about 2.1 t per m³, plus 10% for compaction and waste
- 10 bulk bags (about 0.85 t each), or 1 tipper load (up to 20 t)
How the sum works
Area × depth gives the volume in m³. The calculator multiplies by the material's typical loose density (about 2.1 t per m³ for Type 1, 1.6 for gravel and sharp sand, 1.3 for topsoil) and adds an extra: 10 percent for Type 1, which compacts down, and 5 percent for the others unless you change it.
Bulk bags and loads
A builders' merchant's bulk bag holds roughly 0.85 tonnes, though it varies by merchant and material. Above about 5 tonnes a tipper load is usually cheaper: ask the merchant what their lorry carries and whether it can tip where you need it.
Before you order
Densities change with moisture and grading, so treat the tonnes as a good estimate, not a weighbridge figure. The sub-base depth for a drive or a slab comes from the design, the engineer or building control, not from the calculator.