Concrete calculator
Work out the concrete for a slab, footing, pad or pier, the ready-mix to order, and the cement, sand and gravel if you mix it yourself.
Put these calculators on your phone, free
They work like an app from your home screen, even with no signal on site. On an iPhone: tap Share, then Add to Home Screen. On Android: tap the menu (⋮), then Add to Home screen or Install app.
The free SiteHelm phone app for iPhone and Android is on its way, with every calculator in it. Tell me when it's out
Do more with SiteHelm PRO
Measure slabs and footings off the drawing with Take-off, check the forecast for the pour in Weather, and put the concrete on a purchase order or into your quote. Save it to the job.
Free on your phone. Every builders' calculator will be free in the SiteHelm phone app for iPhone and Android, coming soon. Tell me when it's out.
Every builders' calculator is in SiteHelm PRO for your Windows PC, alongside take-off, RAMS, quotes, invoices and 40+ more tools. The first 100 get a free 1-year licence.
Worked example
A shed base 4 m × 3 m and 100 mm thick, in C20 with 5 percent extra:
1.26 m³ of concrete with 5% extra
- 1.20 m³ before waste
- Ready-mix: order 1.50 m³ (rounded up to the next quarter)
- To mix it yourself at C20 (1:2:4): 17 bags of cement (25 kg), 0.84 t of sharp sand and 1.64 t of 20 mm gravel, or 2.46 t of all-in ballast with the cement
- About 3.02 tonnes once placed
How the sum works
Volume in m³ = length × width × depth, all in metres. A round pad or pier is 3.14 × radius × radius × depth. The calculator adds your waste figure and rounds the ready-mix up to the next 0.25 m³, the step most suppliers sell in.
Mixing it yourself
For each m³ of finished concrete, the calculator allows about 320 kg of cement, 0.67 t of sharp sand and 1.3 t of 20 mm gravel for C20, or 1.95 t of all-in ballast with the cement. C10 and C25 use less and more cement. These are rule-of-thumb site mixes: for anything structural, the mix comes from the engineer or the specification.
Over about a cubic metre, mixing by hand is slow and hard work: compare the price of a ready-mix delivery or a mix-on-site lorry.
Before you order
Measure the open trench or the formwork, not just the drawing: over-dig is the usual reason a pour runs short. Check the supplier's minimum load and the access for the lorry, and the forecast for frost.